1st March 2022, Tuesday
The steel deck sheet structure of the western steel girders in the railway premises of Naigaon East West Bridge has been constructed in 3 days. The railway block concrete work will be completed this week by the RPS Company.
10th February, Thursday
Inauguration of Steel Girder Launching in the Eastern Railway premises of Naigaon East-West Bridge Was performed in the presence of ex Mayor Shri Pravin Shetty, MMRDA Deputy Engineer Mr Bhagvan Chavhan, IOW Western Railway Shri P.K.Sharma. 3 steel girders were launched in yesterday’s railway block and the remaining 2 steel girders will be launched in today’s railway block.
Ex.Corporator Shri Kanhaiya Beta Bhoir
Ex. Corporator Shri Manish Vartak
Ex. Corporator Shri Pravin Vartak
Shri Ashish Vartak
January 2022
On Thursday 27th January, and Friday, 28th January, 5 girders were launched on the west side by RPS company in just 7 hours block received by Railways, and in a few days the remaining 5 girders from Naigaon East will be launched in the same way by the company. Special thanks were extended to MLA Shri Hitendraji Thakur, Ex Mayor Shri Narayanji Mankar, Ex Mayor Shri Pravin Shetty, Corporator Shri Knhaiya Beta Bhoir, Corporator Shri Manish Vartak, Corporator Shri Pravin Vartak and Shri Ashish Vartak for their cooperation in launching the steel girders in the railway area through MMRDA and RPS Company.
December 2021
The span joints will be made immediately after the steel girders assembly work is completed. Approval has also been received from Railways for that work.
October 2021
The readymade steel plates girder of the railway track area (ROB) of Naigaon East-West Bridge has landed at the Naigaon West area.